Canadian flag Made in Canada

AMPLIFY VOLT/SCCR Calculator

Calculate voltage drop and size conductors — Canadian Electrical Code 2024

Auto Cable & Conduit

Minimum cable auto-selected for ampacity + VD budget. Conduit sized by fill calculations.

🔗

Node-Based Topology

Define nodes in the Node Manager, then pick any route in the Calculator tab.

🛡

Full CEC Checks

VD, ampacity, SCCR, bonding (Rule 10-616), GEC (Rule 10-114) all auto-calculated.

⚠️
Information Purposes Only — Verify All Calculations
This calculator is provided as an engineering reference tool for information purposes only. Results are not a sealed engineering document and shall not be relied upon for permit submission, tendering, construction, or any other regulated purpose without independent verification. All calculations must be reviewed, verified, and sealed by a licensed Professional Engineer (P.Eng.) or Master Electrician authorized to practice in the project jurisdiction. Neither the author, I&R Associates, nor Amplify Design Consulting accepts any liability for errors, omissions, misuse, or consequences arising from use of this tool. Use at your own risk.
💾 Save / Load Project
Save your project to a .avolt file. Opens on any computer — no cloud, no account.
🔵
Node Manager
Define all nodes (transformer, panels, disconnects). Configure system settings below, then go to Segment Analysis to wire them up.
💡 Tip: Click a node name to rename it. The + button instantly adds a segment in the Segment Analysis tab. The first node (⚡ Source) is the transformer.
⚡ System Configuration
Phase · Voltage · VD Limits · Cable Rules · Transformer — applies to all segments
≥60A feeder → AL  |  <60A / small size → CU
Auto: optimizer picks cable & sets  |  Manual: you pick, calcs still validate
🎯 VD Design Targets
Flat: your design target applies equally to all feeder/panel/meter-stack nodes. Recommended for most projects.
Warn threshold  |  CEC max 3.0%
Hard fail — CEC Rule 8-102
Load endpoints — CEC max 5.0%
Table D3 K (Ω/km @ 75°C) incl. AC reactance — cable vs raceway column auto per install method
OFF = full-size bond in every raceway (conservative). ON = CEC 10-616(4) division — smaller, code-minimum bonds.
🔧 Practical Cable Limits — Auto-Solve Parallel Logic
⚡ Auto-solve will prefer parallel sets over exceeding these per-set limits.  e.g. 400A in raceway → 2×350 MCM AL instead of 1×1000 MCM AL.
Indoor pulls, tight bends
Duct bank pulling
Pulling machines available
No bending constraints
CEC Table 36 AAC sizes
🏭 Source Configuration (for SCCR)
Utility transformer — ISC from kVA and Z% impedance
⚡ Utility Transformer
Short Circuit Calculation (Bussmann P2P Method)
Available fault-current estimate only — verify equipment interrupting rating/SCCR per CEC Rule 14-012
OFF ON
One-Line Diagram Preview
Segment Analysis
Cable & conduit auto-sized. ISC/VD calculated per segment.

Visual One-Line

Drag nodes to reposition · Drag the amber dot on a node's edge to another node to create a segment
Select a node to see details.
📊 Results & Reports
VD · SCCR · Ampacity · Bonding · GEC · Feeder Notes
Feeder VD — Rule 8-102
0.00%
Limit 3%
Total VD (Source → Load) — Rule 8-102
0.00%
Limit 5%
📉
Voltage Drop Results
CEC Rule 8-102 — 3% feeder / 5% total
#SegmentFrom → ToLength (ft)Conductor SetsCurrent/SetK (CEC)Area mm²CMSeg VD (V)Seg VD% Cum VD%End VoltageStatus
Formula — CEC 2024 Table D3 Method (CSA C22.1 Appendix D)VD = P × I × K × L(m) / 1000  |  K = Table D3 value (Ω/km @ 75°C) including AC reactance at the selected power factor (100/90/80% or DC), cable vs raceway column chosen per install method  |  P = 2 (1φ) or 1.732 (3φ)  |  L = one-way length (ft → m)  |  AAC aerial sizes (266.8–477 kcmil) interpolated between Table D3 rows
Fault Current (SCCR)
Bussmann P2P Method — CEC Rule 14-012
#SegmentLengthC-ValueSets ISC In (A)f FactorM FactorISC Out (A) AIC RatingAIC Status
Bussmann P2Pf = (1.732 × L × ISC_in) / (C × n × V)  |  M = 1/(1+f)  |  ISC_out = ISC_in × M
🔌
Cable Selection Validation (CEC Tables 2/4/D11A/D11B)
Derated ampacity ≥ load current per set
#SegmentConductorTable Base (A)DeratingDerated (A) Load (A)Status
Underground (D11A/D11B): 90°C base ×0.886 for 75°C terminations. Raceway/Free Air: Table 5A ambient derating applied.
🔗
Bonding & Grounding Conductor Requirements
CEC Table 16 / Rule 10-616 and Rule 10-114
⚡ Bonding Conductor Sizing (CEC Table 16 / Rule 10-616)
#SegmentCircuit Ampacity Cu BondingAl BondingCEC Rule
🏠 Grounding Electrode Conductor (CEC Rule 10-114)
Per CEC Rule 10-114(1): Minimum #6 AWG copper or #4 AWG aluminum for services up to 200A.
CEC Rule 8-102 Compliance — Node Status
Cumulative VD from Transformer to each node. Feeder 3% vs Branch/Load 5%
NodeTypeCumulative VD%Targets ▶Design ⚠Warn ✗FailStatusRule
📋
Feeder Notes for Drawings
Auto-generated — copy directly into drawing callouts
Toggle note content ↑
Numbering: Applies to Copy All ↑
Format: [Prefix] [Amps] [Sets]-[Size] [Material] & [Bond] BOND IN [Conduit] [MIN.] [OR EQUAL]  [VD%]
⚠️
Engineering Reference Only. Verify with a Professional Engineer or Master Electrician. CEC CSA C22.1:2024. Bussmann P2P per Eaton Bussmann Short-Circuit Guide.  |  amplifydesign.ca
📋 Calculation Basis & Design Standards
Methodology · Code References · Firm Info · Printable Submittal
🏢 Firm & Engineer Information Appears on printed submittal
🏠 Suite Feeder Schedule Generator Auto-calculates max feeder length per conductor size at your demand current
CEC Classification: Meter Stack → Suite Panel = FEEDER (CEC Rule 8-102 — 3% max cumulative). Suite Panel → Outlets = BRANCH (remaining budget to 5% total). VD budget split: feeder consumes budget from source, branch gets whatever remains.
🔗 Sync with Segment Analysis (for dead-accurate match)
To match a specific suite feeder you designed in Segment Analysis exactly, pick that segment below. The schedule will auto-set voltage, VD budget, design current, and upstream VD. Length rounding will be disabled so distances match exactly.
Upstream (MS feeder) VD: %  ·  Branch remaining: 3%
(5% CEC 8-102 total = upstream + feeder + branch)
⚡ Feeder Breaker (for drawing note)
This value appears on the drawing note only. The schedule math is based on the design current (panel × demand factor), not the breaker size. Cable lug fit to be verified against the specified meter stack supplier.
(Optional) Flags cables that MAY exceed typical panelboard plug-on breaker lug ranges. Meter stack breakers often have looser lug ranges — verify with supplier.
Design Current
100A
VD calculated on this
Max VD Allowed
4.16V
2% × 208V
Feeder Breaker
70A
Next standard above demand
Amplify Design
I&R Design Consultant
amplifydesign.ca
CALCULATION BASIS
Voltage Drop & Short Circuit Analysis
CEC CSA C22.1:2024
Project
Project No.
Engineer
Date / Rev
1 — Design Parameters
ParameterValue SelectedBasis / CEC Reference
System VoltageAs per utility service agreement
Phase Configuration3-wire + neutral per CEC Rule 4-024
Temperature RatingCEC Rule 4-006 — termination rating governs
Conductor MaterialMaterial is a design choice; verify conductor type, equipment listing, and terminal suitability
VD Design Target (Feeder)CEC Rule 8-102 max 3% feeder, 5% total
VD Hard Limit (Feeder)CEC Rule 8-102(1) — mandatory maximum
JurisdictionAlberta, CanadaCSA C22.1:2024 (CEC 2024)
2 — Voltage Drop Calculation Method
Voltage drop is calculated using the CEC Table D3 impedance method per CSA C22.1:2024 Appendix D. Table D3 resistance/reactance values are selected by material, conductor size, installation geometry, and power factor, with the Table D3 Note 3 temperature multiplier applied.
VD (V) = (K × P × L × I) / CM
SymbolDescriptionValue / Source
KCEC Table D3 impedance (Ω/km @ 75°C)CEC 2024 Table D3 — includes AC reactance & power factor
PPhase factor3-phase: 1.732 (√3)  |  Single-phase: 2.000
LOne-way conductor lengthPer design (feet)
ICurrent per conductor setLoad (A) ÷ parallel sets
CMConductor area in circular milsCEC Table D5 (mm²) × 1973.5 conversion factor
Material60°C (K)75°C (K)90°C (K)
Copper (CU)11.712.312.8
Aluminum (AL)19.620.621.6
VD% = (VD ÷ System Voltage) × 100  |  Cumulative VD traced from transformer secondary to each node.
3 — Conductor Ampacity & Derating
Conductor ampacity is selected per applicable CEC tables based on installation method. Where 90°C rated conductors are installed with 75°C rated terminations, ampacity is derated per CEC Rule 4-006 (multiply 90°C table value by 0.886 to obtain 75°C equivalent).
Install MethodCU TableAL TableDerating Basis
Underground Duct BankCEC Table D11ACEC Table D11B90°C base × 0.886 for 75°C terminations (Rule 4-006). Detail column = conduits in duct bank.
Direct BuriedCEC Table D8ACEC Table D8B90°C base × 0.886 for 75°C terminations. Detail 1 or 2 per CEC Diagram D8.
Raceway / ConduitCEC Table 2CEC Table 4Table 5A ambient temperature derating applied at selected ambient °C.
Free AirCEC Table 1CEC Table 3Table 5A ambient temperature derating applied.
Aerial NSC (Bundled)CEC Table 36B (CU)CEC Table 36A (AL)NSC Triplex / Quadruplex. Wind-cooled ambient derating: AL 30°C=1.0, 35°C=0.94, 40°C=0.88 (T36A note 2); CU 30°C=1.0, 35°C=0.92, 40°C=0.84 (T36B note 2). Sizes #6 AWG to 500 kcmil AL, #6–4/0 CU. Includes AAC sizes 266.8, 336.4, 397.5, 477 kcmil.
Parallel sets: each set must individually satisfy ampacity ≥ load ÷ sets. Underground parallel sets must use the corresponding Detail column (e.g. 2 sets = minimum Detail 2) per CEC Diagram D11.
4 — Short Circuit Current (Bussmann Point-to-Point Method)
Available fault current is calculated using the Eaton Bussmann Point-to-Point (P2P) Method per CEC Rule 14-012. Transformer secondary ISC is calculated from nameplate kVA and impedance Z%. Conductor impedance is accounted for using Bussmann C-values (Table 4 of the Bussmann Short-Circuit Guide).
ISCsecondary = FLA × (100 / Z%)  |  f = (P × L × ISCin) / (C × n × V)  |  M = 1 / (1 + f)  |  ISCout = ISCin × M
SymbolDescriptionValue / Source
PPhase factor3-phase: 1.732  |  Single-phase: 2.000
LOne-way conductor length (ft)Per design
CConductor impedance constantBussmann Short-Circuit Guide Table 4 — varies by material, conduit type, cable size
nNumber of parallel setsPer design
VSystem line-to-line voltage (V)Per design
Worst CaseVoltage tolerance factor×0.9 (±10% voltage variation) — conservative per Bussmann guide
C-values sourced from Eaton Bussmann Short-Circuit Current Calculation Guide (Table 4) at 75°C conductor temperature. Four tables used: CU/AL × Steel/Non-Magnetic conduit.
5 — Bonding & Grounding
RequirementCEC RuleSizing Basis
Equipment Bonding ConductorRule 10-616 / Table 16Sized per circuit ampacity — largest overcurrent device protecting that circuit
Grounding Electrode Conductor (GEC)Rule 10-114 / Table 16Sized per service ampacity at point of connection to grounding electrode
System GroundingRule 10-204Neutral grounded at service — one point only per Rule 10-200
6 — Calculation Summary (Live — Auto-Updated)
#SegmentCableSetsMethod TableBase (A)Derated (A)Load (A) Seg VD%Cum VD%ISC OutStatus
7 — Code & Reference Documents
DocumentEditionApplication
CSA C22.1 — Canadian Electrical Code Part I2024 (25th Edition)Primary electrical design standard — all rules cited herein
Eaton Bussmann Short-Circuit Current Calculation GuideCurrentP2P fault current method, C-value tables
CEC Appendix D — Tables D5, D8A/B, D11A/BCSA C22.1:2024Conductor ampacity, circular mil areas, voltage drop
CEC Table 2, 4 (CU/AL Raceway Ampacity)CSA C22.1:2024Conductor ampacity in raceways/conduit
CEC Table 5A (Ambient Derating)CSA C22.1:2024Temperature correction factors for raceway/free air
CEC Table 16 (Bonding/GEC)CSA C22.1:2024Equipment bonding and grounding electrode conductors
Engineering Reference Only. This calculation basis document is generated by the Amplify VD/SCCR Calculator and is intended to support engineering review. All calculations shall be verified by a Professional Engineer (P.Eng) or Master Electrician licensed in Alberta, Canada prior to permit submission. Final design is the responsibility of the engineer of record.

Amplify Design | amplifydesign.ca
🅿
Parking Receptacle Calculator
CEC Rule 8-400 · Rule 26-700(2) · Table 5C bundling · Rule 8-102 VD · CEC conduit sizing
Step-down: conduit reduces as circuits peel off
📍
Receptacle Locations
Enter each stall/receptacle with its wiring distance from panel — circuits auto-group into conduit segments
# Label Distance (ft) Qty / Stalls Phase Pole